Time and Work – Complete Short Notes for Competitive Exams
1. Basic Concept
👉 Work, Time, and Efficiency are directly related:
2. Key Relationship Between Time & Work
-
If A can complete a work in n days,
→ A’s 1 day work = 1/n -
If A’s 1 day work = 1/n,
→ Time taken = n days
Example:
If A can complete work in 10 days → 1 day work = 1/10
If B can complete in 15 days → 1 day work = 1/15
Together in 1 day → (1/10 + 1/15) = 1/6 → Work done in 6 days
3. Work Efficiency Concept
If efficiency ratio of A : B = 2 : 3
→ Time ratio = 3 : 2
(B is faster because more efficient → takes less time)
4. Formula Summary
| Concept | Formula |
|---|---|
| A’s 1-day work | 1 / Time taken |
| Combined work | (A’s + B’s work) |
| Work done in x days | x × (1/Total time) |
| Remaining work | 1 − (Work done) |
| Total work (in units) | LCM of days taken by each person |
| Efficiency | Work units / Days |
5. Combined Work
If A can do a work in x days, and B in y days,
Example:
A = 10 days, B = 15 days
Together = (10×15)/(10 + 15) = 150/25 = 6 days
6. Partial Work Concept
If A & B together can finish work in 6 days, and A alone in 10 days:
A’s 1 day = 1/10,
A+B = 1/6,
So B’s 1 day = 1/6 − 1/10 = 1/15 → B alone can finish in 15 days
7. Work Done or Remaining
Work done = (Days worked / Total days to finish work)
Work left = 1 − Work done
Example:
A completes work in 12 days.
In 8 days → work done = 8/12 = 2/3, work left = 1/3.
8. When A works alone and then with B
If A works alone for x days, then A & B work together for y days:
If total work = 1, substitute and solve for unknown.
Example:
A = 10 days, B = 15 days.
A works 2 days alone, then both work together.
Work done in 2 days = 2/10 = 1/5
Remaining = 1 − 1/5 = 4/5
(A + B) in 1 day = 1/6 → 4/5 ÷ 1/6 = 4.8 days
Total = 2 + 4.8 = 6.8 days
9. More Than Two Persons
If A, B, and C can complete a work in a, b, and c days respectively:
10. Efficiency Ratio
Efficiency ∝ 1 / Time
If A : B :: Time = 3 : 4
Efficiency = 4 : 3
11. Work & Wages Relationship
Wages ∝ Work Done
If A : B = 2 : 3 (work done),
then wages distributed = 2 : 3.
Example:
A, B complete work together and get ₹500.
A’s efficiency : B’s = 3 : 2
Then A : B = 3 : 2 → A = ₹300, B = ₹200
12. Pipes and Cisterns (Application)
Inlet Pipe: Fills the tank (positive work)
Outlet Pipe: Empties the tank (negative work)
| Case | Formula |
|---|---|
| Fill pipe alone | 1/x |
| Empty pipe alone | −1/y |
| Together | 1/x − 1/y |
| Time to fill | 1 / (1/x − 1/y) |
Example:
A pipe fills tank in 6 hr, outlet empties in 9 hr
Net 1 hr work = (1/6 − 1/9) = 1/18
So tank filled in 18 hours
13. Leakage Case
If a tank should fill in x hrs but takes t hrs more due to leakage:
14. Alternate Days Work
If A and B work on alternate days:
-
Find 2-day work = A + B
-
Divide remaining work accordingly
Example:
A = 5 days, B = 10 days
2-day work = (1/5 + 1/10) = 3/10
After 3 such pairs (6 days) → 9/10 done, 1/10 left → next A does 1 day = 1/5 → finish 2 more days → 7 days total
15. Chain Rule in Time & Work
Use the man-days concept:
Example:
10 men finish work in 12 days → 10×12 = 120 man-days
If 15 men work, time = 120/15 = 8 days
16. Important Ratios
| Type | Ratio Relation |
|---|---|
| Time | ∝ 1 / Efficiency |
| Work | ∝ Efficiency × Time |
| Wage | ∝ Work done |
17. Shortcut Table
| Type | Formula |
|---|---|
| Together time (A & B) | (A×B)/(A + B) |
| A’s work in x days | x/A |
| Remaining work | 1 − x/A |
| Work done by A & B | (x/A + x/B) |
| Wages ratio | Work ratio |
| Pipe & Cistern | 1/x ± 1/y |
18. Practice Questions
Q1. A can finish work in 10 days, B in 15 days. Together → ?
= (10×15)/(10 + 15) = 6 days
Q2. A works 2 days alone, then B joins; total 5 days → complete.
Find B’s time if A alone in 10 days.
Let total work = 30 units → A = 3/day, work done in 2 days = 6
Remaining 24 in 3 days → B = (24 − 9)/3 = 5 units/day → B alone = 30/5 = 6 days
Q3. Two pipes fill tank in 10 & 15 hr; third empties in 30 hr.
Effective = (1/10 + 1/15 − 1/30) = 1/6 → Tank filled in 6 hours
19. Quick Revision Chart
| Concept | Formula |
|---|---|
| Work formula | Work = Rate × Time |
| A’s 1-day work | 1/n |
| Combined work | (1/x + 1/y) |
| Together time | xy/(x + y) |
| Efficiency | 1/Time |
| Wages ratio | Work ratio |
| Pipe & Cistern | 1/x ± 1/y |
20. Common Tricks
✅ Always assume total work = LCM of given days.
✅ Efficiency = Work ÷ Time.
✅ Wages distributed by work done.
✅ Pipes filling = +ve, emptying = −ve.
✅ Use “1-day work” method for simplicity.
21. Real-life Concept Links
-
Construction: man-days
-
Pumping, storage, leak detection problems
-
Work allocation & project management
-
Productivity and wage calculation
✅ In One Line:
“Work is done faster by higher efficiency or teamwork — Time × Rate = Work always holds true!”
%20(19).jpg)
0 Comments